thE CritiCAl pAth in A sChEDulE nEtwork is thE pAth thAt: A. tAkEs thE longEst timE to ComplEtE B. must BE DonE BEForE Any othEr tAsks C. Allows somE FlExiBility in sChEDuling A stArt timE. D. is not AFFECtED By sChEDulE slippAgE E. All oF thE ABovE.