【单选题】
When there is uncertainty associated with one or more aspects of the project.one of the first steps to take is to______.
A.revise project plan
B.conduct a risk benefit analysis
C.conduct a needs analysis
D.increase the estimated cost of the project
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
16%的考友选择了A选项
74%的考友选择了B选项
6%的考友选择了C选项
4%的考友选择了D选项