【单选题】

An example of risk mitigation is______.
A.using new technology in the development of a product

B.purchasing insurance
C.eliminating the cause of risk
D.accepting a lower profit if costs overrun
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

43%的考友选择了B选项

54%的考友选择了C选项

1%的考友选择了D选项