You are in the process of developing options,and determining actions to enhance opportunities and reduce threats to the project's objectives.What should you be doing next
A.Determining which risks might affect the project and documenting their characteristic

B.Identifying,analyzing and planning for newly arising risk
C.Deciding how to approach and conduct risk management activities for the projec
D.Assessing the priority of identified risks using their probability of occurin
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

20%的考友选择了A选项

68%的考友选择了B选项

0%的考友选择了C选项

12%的考友选择了D选项