Resource calendars affect a specific resource or category of resources. They reflect how some resources work only during normal business hours, while others work three full shifts, or a project team member might be unavailable, such as on vacation or in a training program, or a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs for ______ .

A、developing an approximation of the costs of the resources needed to complete each schedule activity
B.aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance
C.searching the cause of positive and negative variances as part of integrated change control process
D.assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

如答案有误或试题有侵权,请联系我们。[提交反馈][在线客服]

根据网考网移动考试中心的统计,该试题:

36%的考友选择了A选项

53%的考友选择了B选项

5%的考友选择了C选项

6%的考友选择了D选项

你可能感兴趣的试题

Inyourproject,youwanttomonitorandcontrolTheknowledgeareathatdescribestheprocesseWhenshouldlessonslearnedbeorganizedA.DurYouhavebeenworkingonaverylargesoftwaredeAprocurementauditisastructuredreviewofthCalculatethestandarddeviationofataskifO=
版权所有网考网(netkao.com)All Rights Reserved

警告:系统检测到您的账号存在安全风险

抱歉,您的账号因涉嫌违反网考网购买须知被冻结。您可在“网考网” 微信公众号中的“官网服务”- "账号解封申请”申请解封。

微信扫描关注网考网