试题查看

首页 > PMP考试 > 试题查看
【单选题】

The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called ______ .
A.parametric estimation

B.create WBS
C.feasibility analysis
D.benefit-cost analysis
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

23%的考友选择了A选项

66%的考友选择了B选项

3%的考友选择了C选项

8%的考友选择了D选项

你可能感兴趣的试题

AllofthefollowingareexamplesofasourceofsAnoutputofscopedefinitionis______.A.workThedecompositionprocessisatechniqueusedtAprecisiondescriptionofadeliverableiscalWhichofthefollowingstatementsistrueaboutTheidentification,definitionandselection