The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called ______ .
A.parametric estimation
B.create WBS
C.feasibility analysis
D.benefit-cost analysis
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
23%
的考友选择了A选项
66%
的考友选择了B选项
3%
的考友选择了C选项
8%
的考友选择了D选项