【单选题】

Due to cuts in funding, your project has been terminated. The scope verification process ______ .
A.should be delayed until the project is completed

B.should determine the correctness of the work results
C.should establish and document the level and extent of completion
D.will form the basis of the project audit
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

1%的考友选择了A选项

5%的考友选择了B选项

88%的考友选择了C选项

6%的考友选择了D选项