【单选题】

A management control point can be placed at selected management points (specific components at selected levels)of the WBS above. the work package level. These control points can be ______ .
A.used for rolling wave planning

B.decomposed further to help in creation of work authorization system
C.used for planning known work content that does not have detailed schedule activities
D.used as a basis for planning when associated work packages have not yet been planned
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

10%的考友选择了A选项

6%的考友选择了B选项

22%的考友选择了C选项

62%的考友选择了D选项