【单选题】
All of the following would occur during the closure of the project EXCEPT______.
A.creating lessons learned
B.formal acceptance
C.reducing resource spending
D.performing benefit cost analysis
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
2%的考友选择了A选项
9%的考友选择了B选项
1%的考友选择了C选项
88%的考友选择了D选项