试题查看
首页
>
PMP考试
> 试题查看
【单选题】
What is the process for aggregating the estimated costs of individual activities or work packages to establish a cost baseline known as
A.Cost assessmen
B.Determine budge
C.Plan contractin
D.Cost estimatin
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
40%
的考友选择了A选项
55%
的考友选择了B选项
2%
的考友选择了C选项
3%
的考友选择了D选项
你可能感兴趣的试题
AsperPMBOK,variousexecutingprocessesfall
Allofthefollowingwouldoccurduringtheclos
Aprojectmanagerlearnsthatcorrectiveactio
Whichtypeofinputistheprimarycauseofcontr
Youaremanagingaprojectinaforeigncountry,
Youareassignedastheprojectmanagerinthemi