【单选题】
Which of the following are the most commonly used performance measures of evaluating whether or not work is being accomplished as planned at any given point of time
A.PV & A
B.AC,EV & P
C.CV & S
D.SPI,EV & A
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
17%
的考友选择了A选项
70%
的考友选择了B选项
8%
的考友选择了C选项
5%
的考友选择了D选项