The client demands changes to the product specification that will add only two weeks to the critical path.Which of the following is the best thing for the project manager to do
A.Compress the schedule to recover the two week

B.Cut scope to recover the two week
C.Consult with the sponsor before taking any actio
D.Advise the client of the impact of the chang
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

8%的考友选择了A选项

17%的考友选择了B选项

5%的考友选择了C选项

70%的考友选择了D选项