During a project the scope of a product purchased on a cost reimbursable contract has increased.In the contract the fee to cover the contractor's indirect costs and allow a profit is calculated as 20% of the direct costs.What is most likely to be true
A.The contractor's indirect costs will increase and the customer's payment for them will increase,to

B.The contractor's indirect costs will increase but the eLlstomer's payment for them will not increas
C.Neither the contractor's indirect costs nor the customer's payment for them will increas
D.The contractor's indirect costs will not increase but the customer's payment for them will increas
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

63%的考友选择了A选项

36%的考友选择了B选项

0%的考友选择了C选项

1%的考友选择了D选项