【单选题】

A project manager has to resolve two problems. However, both problems can occur in a single trial. In this situation, what is the BEST action the project manager can take
A.Develop a solution for each proble

B.Develop a solution that solves both problem
C.Use a statistically independent tria
D.N0 solution is needed, the two problems cancel each other ou
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

7%的考友选择了A选项

67%的考友选择了B选项

16%的考友选择了C选项

10%的考友选择了D选项