【单选题】

The primary method of reducing conflict in projects is to ______ .
A.hold periodic group meetings

B.use group facilitators
C.perform careful project planning
D.enforce strict rules about arguing
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

8%的考友选择了A选项

29%的考友选择了B选项

61%的考友选择了C选项

2%的考友选择了D选项