试题查看

首页 > PMP考试 > 试题查看
【单选题】

Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

A 11, 13
B 12, 14
C 13, 15
D 14, 16
E 15, 17
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

52%的考友答对了

你可能感兴趣的试题

AsaprojectiscarriedoutandslacktimeisconsThepurposeofadummyactivityinanactivity-oOnNovember1,$1000worthofworkontaskAwassuAplanhasbudgetedthreeweeksofeffortforconResourcelevelingwilloftenaffecttheprojecUsingthefigureintheSpecialwindow,Theslac