试题查看

首页 > PMP考试 > 试题查看
【单选题】

Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . 

A Slack for each activity, critical path. 
B Slack for each activity, high risk activities. 
C Manpower shortages, high risk activities. 
D High risk activities, non-critical paths. 
E Manpower availability, contingency plans. 
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

71%的考友答对了

你可能感兴趣的试题

SchedulingsystemssuchasPERT,ADM,andPDMarIncreasingresourcesonthecriticalpathactiAlinemanagerprovidesyouwiththreeestimateManagementhasdecidedto"crash"aprojectinoAnetworkhasbeendevelopedwithresourcesfroBarchartsaremostappropriatefor:AComparin