Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A Slack for each activity, critical path. B Slack for each activity, high risk activities. C Manpower shortages, high risk activities. D High risk activities, non-critical paths. E Manpower availability, contingency plans.