【单选题】

The starting point in the development of a top-down PERT/CPM chart is the _____ .

A Project specification tree. 
B Customer's deliverable list. 
C Customer's milestone dates. 
D Work breakdown structure. 
E Listing of customer team meeting dates.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...