The major difference between PERT and CPM networks is:
A PERT requires three time estimates whereas CPM requires one time estimate. B PERT is used for construction projects whereas CPM is used for R & D. C PERT addresses only time whereas CPM also includes cost and resource availability. D PERT requires computer solutions whereas CPM is a manual technique. E PERT is measured in days whereas CPM uses weeks or months.