【单选题】
During the project scope planning process, the work breakdown structure should be developed to ______ .
A.the sub-project level
B.the level determined by the project office
C.a level allowing for adequate estimates
D.the cost center level
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
10%的考友选择了A选项
6%的考友选择了B选项
62%的考友选择了C选项
22%的考友选择了D选项