【单选题】
To ensure the project team provides the functionality the customer expects in a new piece of software, the project manager asks the customer for sign-off on the design criteria. These documents are ______ .
A.technical specifications
B.performance specifications
C.product descriptions
D.quality assurance
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
70%
的考友选择了A选项
8%
的考友选择了B选项
0%
的考友选择了C选项
22%
的考友选择了D选项