试题查看

首页 > PMP考试 > 试题查看
【单选题】

To ensure the project team provides the functionality the customer expects in a new piece of software, the project manager asks the customer for sign-off on the design criteria. These documents are ______ .
A.technical specifications

B.performance specifications
C.product descriptions
D.quality assurance
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

70%的考友选择了A选项

8%的考友选择了B选项

0%的考友选择了C选项

22%的考友选择了D选项

你可能感兴趣的试题

Duetocutsinfunding,yourprojecthasbeenterAKEYactivityforachievingcustomersatisfacDuringtheprojectscopeplanningprocess,theAmanagementcontrolpointcanbeplacedatseleAscopestatementisimportantbecauseit_____Acustomerisnothappywithaprojectdeliverab