【单选题】
In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A.PERT
B.CPM
C.parametric estimating
D.none of the above
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...