试题查看

首页 > PMP考试 > 试题查看
【单选题】

In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A.PERT

B.CPM
C.parametric estimating
D.none of the above
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

56%的考友选择了A选项

9%的考友选择了B选项

2%的考友选择了C选项

33%的考友选择了D选项

你可能感兴趣的试题

Yougotnewsthatbecauseofbadweather,yourshTheobjectiveoffasttrackingaprojectisto__IfyouarecalculatingoneearlystartandearlyAllthefollowingareadvantagesofGERT(graphYourscheduleanalysishasshownthatyourprojAllofthefollowingaretrueaboutresourcelev